Project Brief

Location: Tiffin Girls’ School, Kingston upon Thames – Ground Floor Corridor

Sector: Education

The ground floor corridor at Tiffin Girls’ School required a flooring upgrade to refresh a high-traffic area used daily by staff and students.

The brief called for durable, modern carpet tiles that would provide both resilience and a contemporary aesthetic, installed with minimal disruption to the school’s operations.

Tiffin 3
Tiffin 5

5 Key Steps in the Design Process

01

Planning & Presentation

A detailed site survey and precise measurements were taken to confirm requirements and prepare for a seamless installation. Existing Milliken carpet tiles were then uplifted and cleared to on-site waste skips, leaving the corridor ready for works.

02

Subfloor Check

The exposed subfloor was inspected to ensure it was clean, level, and suitable for the new installation, with minor adjustments made where necessary.

03

Material Preparation

Interface Employ Dimensions carpet planks tiles in colour Line (Purple/Grey) were delivered and staged for efficient laying.

This well-planned project delivered a stylish, practical and hard wearing finish completed during a weekend to avoid any disruption to school activities.

05

Completion & Handover

The project was carried out over a weekend to avoid disruption to school activities. The corridor was completed on schedule, providing a refreshed, durable, and visually striking finish ready for immediate use.

04

Installation

The carpet tiles were installed across 110m² of corridor space using the manufacturer’s recommended adhesives, ensuring a secure and long-lasting finish.

What we did

  • Carried out detailed site survey and precise measurements

  • Uplifted and cleared existing Milliken carpet tiles to on-site skip

  • Inspected and prepared subfloor for installation

  • Supplied and staged Interface Employ Dimensions Carpet Planks 1000mm × 250mm tiles (Colour Line – Purple/Grey)

  • Installed tiles using manufacturer’s recommended adhesives

  • Delivered and completed 110m² installation over a weekend

  • Achieved a durable, high-quality finish with minimal disruption

What our clients say…

Creed-Miles Preferred Partner for Outstanding Offices.

icon teamwork

Professional,
Friendly Experts

Our reliable and easy to work with team puts your needs first.

icon management

Project Manager

You will have a dedicated project manager on your side from sales enquiry to project completion.

icon knowledge

Collective Knowledge

We then bring together the collective knowledge of our full office fit out team to ensure we deliver the best service and results, on time and to budget.