Dilapidate all installations from outgoing tenant and replicate previously supplied design and feel
open office
Surbiton-london
7 weeks
BRIEF
To dilapidate all installations from outgoing tenant to floor space of 47,500 square foot and replicate design and feel to what we had previously supplied and installed to the 4 other floors in the building.
To work with the facilities team with regards to a furniture inventory from other floors that could be used and what new furniture was required.
To work with nominated contractors from the client and manage and programme their installations.
THE SOLUTION
Having worked with the client over many years to the other 4 floors to the same building an amazing working and trusting relationship had already formed making these works and the understanding of what the client required slightly easier than usually.
After plans and designs were signed off a detailed furniture schedule was created of what could be relocated from other floors and what new furniture was required.
Weekly site meetings were arranged with all contractors to go through progress of works and design tweaks that could be made along the way to make sure we got the best out of every inch of the floor space for the client.
WHAT WE DID
Complete CDM package
Designated CDM Principal Contractor role
Dilapidation works to CAT A spec from previous tenant
Installation of new plasterboard and glass partition walls
Design and installation of new kitchen / tea points
Decoration of all walls and woodwork
Installation of new carpet tiles and rubber stud tiles to kitchen / tea points
Supply and installation of top up furniture
Supply and installation of new roller blinds
Management of installation of HVAC, fire alarm systems, electrical and data contractors
Having worked with the client over many years to the other 4 floors to the same building an amazing working and trusting relationship had already formed.