Project Brief

Location: ACS International School, Egham
Sector: Education

As part of a full refurbishment to modernise the student toilet facilities, the project involved complete strip-out and rebuild works.

The goal was to deliver a clean, durable, and hygienic environment using robust materials, modern sanitaryware, and high-spec finishes, all executed within term time and under tight coordination to minimise disruption.

Commercial Washroom Refurbishment 2
Commercial Washroom Refurbishment 4

Key Requirements

01

Planning & Preparation

Comprehensive site assessments were carried out to sequence the strip-out and rebuild around occupied areas. Protective measures were installed to safeguard surrounding finishes, and waste disposal routes were agreed in advance for efficient delivery.

02

Strip-Out Works

Existing flooring, ceilings, partitions, doors, and sanitaryware were carefully removed and responsibly disposed of via on-site skips. All plumbing and electrical connections were safely isolated and capped, preparing the area for reconstruction.

03

Construction & Fit-Out

New stud partitions were installed using metal framing with acoustic insulation and double-skin sound bloc plasterboards. MF ceilings with access panels were fitted, and new laminate doors with satin stainless-steel ironmongery completed the layout.

This completed refurbishment transformed the student washroom facilities, delivering a modern, hygienic, and durable environment. Completed within term time through precise planning and coordination, the result is a bright, contemporary space that enhances functionality, safety, and cleanliness while minimising disruption to school activities.

05

Finishes & Handover

Floors were prepared with new ply and screed, then finished in Altro Aquarius safety vinyl with full cap and cove detail for hygiene and ease of maintenance. Walls received white roc panels and diamond paint, complemented by large mirrors and silicone-sealed junctions. Final testing, cleaning, and commissioning were completed before handover.

04

Mechanical & Electrical Installations

New plumbing runs were installed to suit the revised layout, feeding Venesta sanitaryware including wash troughs, WCs, and urinals. Dyson Airblade hand dryers, PIR lighting, and new ventilation systems were added for efficiency, safety, and energy performance.

What we did

  • Full strip-out of existing toilets including partitions, ceilings, and sanitaryware

  • Installed new acoustic stud partitions and MF ceilings with access panels

  • Supplied and fitted new Venesta sanitaryware and wash troughs

  • Installed Dyson Airblade hand dryers and PIR lighting systems

  • Supplied and laid Altro Aquarius safety vinyl with cap and cove finish

  • Decorated all walls, ceilings, and woodwork in durable finishes

  • Installed new mirrors, white roc wall panels, and skirting details

  • Carried out all plumbing, heating, ventilation, and electrical works

  • Completed project on time and within normal working hours

What our clients say…

Creed-Miles Preferred Partner for Outstanding Offices.

icon teamwork

Professional,
Friendly Experts

Our reliable and easy to work with team puts your needs first.

icon management

Project Manager

You will have a dedicated project manager on your side from sales enquiry to project completion.

icon knowledge

Collective Knowledge

We then bring together the collective knowledge of our full office fit out team to ensure we deliver the best service and results, on time and to budget.